Trench Calculator
Calculate trench bank volume in cubic yards and loose haulage volume — adjust for swell and waste. Enter excavation dimensions to get instant results. Enter dimensions, select units and add waste to get instant, supplier-ready numbers.
Enter dimensions above to calculate
- Enter values to see step-by-step substitution.
Engineering Assumptions:
- Vertical rectangular excavation. Sloped sides, working room, overbreak and irregular ground need separate measured allowances.
- The cost basis is bank cubic yards. Loose haulage volumes are shown separately. Swell is not a second waste allowance.
Advertisement — after results
Reserved for AdSense — no layout shift.
TOP VIEW — Length × Width
SECTION — Excavation depth 3ft
What Is This Calculator?
The Trench Calculator — Volumes earthwork for US trenches and grading — cut, fill, backfill and soil weight.
What Does It Calculate?
- Trench volume in cubic yards
- Backfill less pipe volume
- Soil weight in tons with swell
How to Use the Calculator
- Measure Trench 20 ft x 2 ft x 4 ft deep — use feet for length/width and inches for thickness where typical.
- Enter values and select units. The calculator converts to feet before calculating (inches /12, yards x3).
- Adjust waste % and optional price, then click Calculate. Results show with waste included.
- Use Reset to clear and try another size.
Formula & Engineering Methodology
Bank volume = length × width × depth; loose volume = bank volume × (1 + swell / 100).
- Volume — Cubic yards with swell 1.2x
- Depth — Feet or inches
All units convert to exact standard engineering dimensions (NIST SP 811) before calculation to ensure consistency between US Customary and Metric measurements.
Worked Example
Example: Trench 20 ft x 2 ft x 4 ft deep
| STEP | VALUE |
|---|---|
| Volume ft3 | 20*2*4 =160 ft3 |
| Yards | 160/27 =5.93 yd3 |
| With swell 1.2x | 7.11 yd3 |
Construction Information
Material: Soil swells 15–25% when dug (1.2x). Clay 1.6 t/yd3, sand 1.5, topsoil 1.2. Call 811 before dig.
Soil swells 15-25% when dug (1.2x). Clay 1.6 t/yd3, call 811.
Material Information
Soil swells 15–25% when dug (1.2x). Clay 1.6 t/yd3, sand 1.5, topsoil 1.2. Call 811 before dig.
Waste & Overages
Trench sides slough — add 10% for over-excavation. Shrinkage 10% on backfill.
Practical Tips
- Bench or slope sides per OSHA over 5 ft
- Stockpile topsoil separate from subsoil
Common Mistakes
- Forgetting swell — truck count short
- Not subtracting pipe volume for backfill
Assumptions & Engineering References
- Vertical rectangular excavation. Sloped sides, working room, overbreak and irregular ground need separate measured allowances.
- The cost basis is bank cubic yards. Loose haulage volumes are shown separately. Swell is not a second waste allowance.
This calculator provides an estimate based on your inputs. Actual requirements vary by site, material and installation. For code-regulated or load-bearing work, consult a qualified professional.
Calculations run 100% in your browser — zero tracking of your dimensions or input data.
Related calculators
Excavation Calculator
Calculate excavation bank volume in cubic yards and loose ha...
Excavation Cost Calculator
Estimate excavation cost — material, quantity and price with...
Trench Volume Calculator
Calculate trench volume in cubic yards and cubic feet — ente...
Trench Backfill Calculator
Calculate trench backfill bank volume in cubic yards and loo...
Earthwork Calculator
Calculate earthwork bank volume in cubic yards and loose hau...
Cut and Fill Calculator
Calculate cut and fill — cut and fill bank balance with shri...
Frequently asked questions
What does the Trench Calculator calculate?
The Trench Calculator estimates trench quantity for US jobs — Trench volume in cubic yards, Backfill less pipe volume, Soil weight in tons with swell. Enter dimensions, choose units, add waste and price to get instant results.
How do I measure for trench?
Measure trench 20 ft x 2 ft x 4 ft deep on site. Use the unit selectors — the tool converts inches→feet (÷12) and yards→feet (×3) before math. For non-rectangular, split into rectangles and add.
How much waste should I add?
Trench sides slough — add 10% for over-excavation. Shrinkage 10% on backfill.
How accurate is this trench estimate?
Math is exact for your inputs. Actual needs vary by site, material and installation. Add 5–10% waste for rectangular, 10–15% for irregular.
About Calculator Street
Built by Vipul Otari for US homeowners & contractors. Calculator inputs are processed in your browser. Estimates depend on your measurements, product specifications and the assumptions shown on this page. Confirm order quantities with your supplier and structural requirements with your project designer. Page updated: 2026-09-11.